Complete Guide to Solar Power in Haryana
Everything you need to know about solar installation, subsidies, DHBVN process, state policy, and electricity savings in Haryana
Solar Power Potential in Haryana
Haryana receives excellent solar irradiation making it ideal for solar power generation
Average daily solar irradiation across Haryana
Excellent sunshine duration throughout the year
Expected annual energy generation per kW installed
| District | DISCOM | Solar Potential | Type |
|---|---|---|---|
| Gurgaon | DHBVN | Very High | Urban |
| Faridabad | DHBVN | High | Urban |
| Panipat | UHBVN | High | Industrial |
| Ambala | UHBVN | High | Mixed |
| Karnal | UHBVN | Medium-High | Agricultural |
| Hisar | UHBVN | Very High | Agricultural |
| Rohtak | UHBVN | High | Mixed |
| Sonipat | UHBVN | High | Urban |
Solar Subsidies Available in Haryana
Central government MNRE subsidy available for residential rooftop solar in Haryana
Subsidy Structure
- • First 3 kW: ₹18,000 per kW = ₹54,000
- • 3-10 kW: ₹9,000 per kW = ₹63,000
- • Maximum total subsidy: ₹78,000
Eligibility
- ✓ Residential consumers only
- ✓ Grid-connected rooftop solar
- ✓ ALMM listed solar panels
- ✓ MNRE empanelled vendor installation
Processing Time
45-90 days through DHBVN/UHBVN
5 kW System
10 kW System
Note: Maximum subsidy capped at ₹78,000 for residential systems
Haryana Solar Power Policy 2024-2025
Progressive policy framework supporting residential and commercial solar adoption
Haryana offers net metering up to sanctioned load with annual banking facility
Sell excess power to grid
DHBVN/UHBVN provide streamlined approval process with clear timelines
30-45 day approval
Solar generation exempt from electricity duty charges in Haryana
Additional 6-8% savings
Solar installations get priority in grid connectivity and net meter installation
Faster commissioning
For Residential
- ✓Net metering up to sanctioned load
- ✓Annual banking facility for excess generation
- ✓Simplified approval through DHBVN/UHBVN
- ✓Exemption from electricity duty
- ✓Priority grid connectivity
For Commercial/Industrial
- ✓Gross/net metering options available
- ✓Banking facility with annual settlement
- ✓Accelerated depreciation benefits
- ✓Open access for large consumers
- ✓Group net metering for industrial parks
Step-by-Step DHBVN Solar Application Process
Complete guide to applying for solar net metering with DHBVN in Haryana
Download Application Form
1 dayVisit DHBVN official website and download the rooftop solar net metering application form. Fill in consumer details, proposed system capacity, and technical specifications.
Required Documents:
- • Net metering application form
- • Consumer electricity bill copy
- • ID proof (Aadhaar/Passport)
Prepare Technical Documents
2-3 daysPrepare all required technical documents including system design, single line diagram, and equipment specifications.
Required Documents:
- • Single line diagram (SLD)
- • Roof ownership proof
- • Property tax receipt
- • Solar panel and inverter datasheets
Submit to DHBVN
1 daySubmit completed application with all documents to nearest DHBVN office or through online portal. Keep acknowledgment receipt.
Required Documents:
- • All above documents
- • Processing fee payment receipt
DHBVN Review & Approval
30-45 daysDHBVN reviews application, conducts feasibility study if needed, and grants approval with technical requirements and connection agreement.
Required Documents:
- • DHBVN approval letter received
System Installation
2-7 daysInstall solar system by MNRE empanelled vendor following DHBVN technical standards. Use ALMM listed panels, approved inverters with anti-islanding protection.
Required Documents:
- • Installation completion certificate
- • Commissioning report
Request DHBVN Inspection
7-15 daysInform DHBVN about installation completion and request inspection. DHBVN team visits site to verify compliance with technical standards.
Required Documents:
- • Inspection request letter
- • Test certificates
Net Meter Installation
3-7 daysUpon successful inspection, DHBVN installs bidirectional net meter. System is commissioned and starts feeding power to grid.
Required Documents:
- • Net meter installation certificate
Total Timeline: 60-90 days from application to commissioning
Xrossways Solar handles the complete DHBVN process for you - from application submission to final commissioning. We ensure all documents are correct for first-time approval.
Haryana Electricity Tariff & Solar Savings
High electricity tariffs make solar economically attractive in Haryana
| Consumption Slab | Rate per Unit | Typical Monthly Bill | Solar Savings |
|---|---|---|---|
| 0-150 units | ₹3.35 | ₹500 | 70% |
| 151-800 units | ₹5.75 | ₹4,600 | 75% |
| 800+ units | ₹7.10 | ₹7,100+ | 80% |
DHBVN/UHBVN net metering allows you to:
- ✓Sell excess power to grid at ₹3-4 per unit
- ✓Monthly billing with annual settlement
- ✓Carry forward excess units up to 1 year
- ✓Offset high consumption months with surplus
Potential additional income: ₹2,000-4,000/month from excess generation
Haryana Solar Success Stories
Real installations across Haryana showing savings and environmental impact
Location
DLF Phase 3
System Size
15 kW
Monthly Savings
₹8,500
CO₂ Offset
18 tons/year
"DHBVN approval was smooth. Our electricity bill reduced from ₹12,000 to ₹2,500. System has been flawless for 18 months."
- Rajesh Kumar, Homeowner
Location
Sector 37
System Size
25 MW
Annual Savings
₹2.64 Cr
CO₂ Offset
37,500 tons/yr
"Largest rooftop installation in Haryana. DHBVN approval in 45 days. Zero production disruption during installation."
- Amit Kumar, Operations Director, GreenTech Manufacturing
Location
Panipat District
System Size
20 kW
Monthly Savings
₹12,000
Subsidy
₹4 lakh
"Agricultural solar subsidy plus MNRE subsidy made this very affordable. Powers irrigation pumps completely. UHBVN was very supportive."
- Harpreet Singh, Farmer
Frequently Asked Questions - Haryana Solar
Common questions about solar power in Haryana
Haryana residential consumers are eligible for MNRE central government subsidy: ₹18,000 per kW for first 3 kW and ₹9,000 per kW for 3-10 kW (maximum ₹78,000). Haryana does not have additional state subsidy but offers excellent net metering with annual banking facility through DHBVN and UHBVN.
DHBVN (Dakshin Haryana Bijli Vitran Nigam) serves South Haryana including Gurgaon, Faridabad, Rewari, Palwal, and surrounding areas. UHBVN (Uttar Haryana Bijli Vitran Nigam) serves North Haryana including Ambala, Karnal, Panipat, Rohtak, Hisar. Both handle solar net metering applications.
DHBVN solar net metering approval timeline: Application review (30-45 days), Installation after approval (2-3 days residential, 1-2 weeks commercial), DHBVN inspection (7-15 days), Net meter installation (3-7 days). Total process takes 2-3 months from application to commissioning.
Haryana DHBVN/UHBVN residential tariffs: ₹3.35/unit (0-150 units), ₹5.75/unit (151-800 units), ₹7.10/unit (above 800 units). Commercial tariffs range ₹6-8/unit. High tariffs make solar very cost-effective with 2.8-3.5 year payback period.
Yes, DHBVN provides net metering with annual banking facility. Excess solar generation is credited at average power purchase cost (₹3-4 per unit). Units are carried forward monthly and settled annually. This allows you to offset higher consumption months with surplus generation months.
Haryana Solar Power Policy focuses on: (1) Net metering up to sanctioned load for residential/commercial, (2) Annual banking facility for excess generation, (3) Simplified approval process through DHBVN/UHBVN, (4) Exemption from electricity duty on solar generation, (5) Priority grid connectivity, (6) Support for agricultural solar pumps.